BENEFIT COST ANALYSIS (BCA)

5 FAH-5 H-610 
USING THE BENEFIT COST ANALYSIS

(CT:ITS-4;   06-21-2012)
(Office of Origin:  IRM/BMP/GRP/GP)
(Updated only to revise Office of Origin)

5 FAH-5 H-611  GENERAL

(TL:ITS-1;   02-13-2002)

a. The current laws relating to managing information technology (IT) in the Federal Government require a Benefit Cost Analysis (BCA) prior to implementing an IT project.

b. The requirement for BCA comes from OMB Circular A-130, to prepare and update, as necessary, throughout the information system life cycle, for each information system.  This is consistent with the methodology described in OMB Circular No. A-94, “Guidelines and Discount Rates for Benefit Cost Analysis of Federal Programs.”

c.  This chapter contains instructions for preparing a BCA for an IT project in the Department of State.

5 FAH-5 H-612  APPROVAL THRESHOLDS

(TL:ITS-1;   02-13-2002)

When an information technology initiative exceeds $30M over the system life cycle, or exceeds $10M in any one year a BCA is required.  In the Department of State, a BCA is required for development and/or integration and/or maintenance projects that exceed $100,000.  Managers must tailor the BCA effort to the size of the project.

5 FAH-5 H-613  SIMPLIFIED BCA

(TL:ITS-1;   02-13-2002)

Use a simplified BCA when the projected cost is $10M or less.  This is a scaled down version of a BCA that focuses only on those elements that the project manager deems relevant.  Projects with life cycle costs below $10M may be justified using a simplified BCA.

5 FAH-5 H-614  THROUGH 5 FAH-5 H-619  
UNASSIGNED

(TL:ITS-1;   02-13-2002)

 